Question Detail

COS 102 introduction to programming Objective Question

Question

A significant deficiency of the Waterfall Model is that it often leads to 'one big bang' at the end. What does this refer to?
Options
A A sudden, massive release of marketing materials.
B A single, extensive integration of all components at the end of the project.
Correct Answer
C A major budget overrun due to unforeseen costs.
D A grand celebration upon project completion.
Correct Answer

Option B is the correct answer.

Detailed Explanation

Page 37 lists among Waterfall Deficiencies: 'Integration is one big bang at the end', meaning all components are integrated at once, rather than incrementally.

Hint

Look for the deficiencies of the Waterfall Model on page 37, specifically 'Integration'.

Question Info