COS 102 introduction to programming Objective Question

Question

Which of the following is a strength of the V-Shaped Model?
Options
A It handles iterations or phases easily.
B It does not easily handle dynamic changes in requirements.
C It allows project management to track progress by milestones.
Correct Answer
D It contains extensive risk analysis activities.
Correct Answer

Option C is the correct answer.

Detailed Explanation

Page 41 states that a strength of the V-Shaped Model is that 'Project management can track progress by milestones'. Options A, B, and D are listed as weaknesses on page 42.

Hint

Consider how the V-Shaped model's structure facilitates project oversight.