COS 102 introduction to programming Objective Question

Question

What is a significant deficiency of the Waterfall Model mentioned in the document?
Options
A It promotes early customer involvement.
B All requirements must be known upfront, inhibiting flexibility.
Correct Answer
C It delivers an operational product at each phase.
D It offers steady, visible signs of progress.
Correct Answer

Option B is the correct answer.

Detailed Explanation

Page 37 states: 'All requirements must be known upfront' and 'Deliverables created for each phase are considered frozen - inhibits flexibility' are deficiencies.

Hint

Think about the rigidity of the Waterfall approach.