COS 102 introduction to programming Objective Question

Question

In the Spiral SDLC Model, what activity is typically performed in the 'Evaluate alternatives; Identify, resolve risks' quadrant?
Options
A Creating a design and developing code.
B Planning the next phase and developing a project plan.
C Studying alternatives relative to objectives and identifying potential risks.
Correct Answer
D Determining objectives, alternatives, and constraints for the entire project.
Correct Answer

Option C is the correct answer.

Detailed Explanation

Page 59 describes this quadrant's activities as 'Study alternatives relative to objectives and constraints' and 'Identify risks (lack of experience, new technology, tight schedules, poor process, etc.'

Hint

The name of the quadrant directly implies its purpose.