COS 102 2 lecture week 3 Objective Question

Question

In the Rapid Application Model (RAD), which phase includes the use of productivity tools like code generators and screen generators within a time-box?
Options
A Requirements planning phase
B User description phase
C Construction phase
Correct Answer
D Cutover phase
Correct Answer

Option C is the correct answer.

Detailed Explanation

Page 49 defines the 'Construction phase' as utilizing 'productivity tools, such as code generators, screen generators, etc. inside a time-box.'

Hint

The question asks about the phase where actual development and tool usage for code generation occurs.