Question Detail

COS 102 2 lecture week 3 Objective Question

Question

When is the Incremental Model particularly useful regarding project requirements?
Options
A When all requirements are known upfront and stable.
B When most requirements are known upfront but are expected to evolve over time.
Correct Answer
C When the project has low technical risks and no need for early functionality.
D When the development schedule is short and fixed.
Correct Answer

Option B is the correct answer.

Detailed Explanation

Page 56 indicates that the Incremental Model is used when 'Most of the requirements are known up-front but are expected to evolve over time.'

Hint

Consider situations where requirements are not entirely static but have a known baseline.

Question Info