Question
What is a significant weakness of the Spiral Model, especially for small or low-risk projects?
Correct Answer
Option C is the correct answer.
Detailed Explanation
Page 63, under 'Spiral Model Weaknesses,' notes, 'Time spent for evaluating risks too large for small or low-risk projects.'
Hint
The Spiral Model is heavily risk-driven. What might be a drawback of this extensive risk analysis for simpler projects?