A significant strength of the Spiral Model is its ability to provide early warning regarding project risks. What specific aspect of risk is indicated early?
Options
A Early indication of insurmountable risks
Correct Answer
B Early identification of minor defects
C Early feedback on user interface design
D Early assessment of cumulative costs
Correct Answer

Option A is the correct answer.

Detailed Explanation

Page 62 states that a strength of the Spiral Model is that it "Provides early indication of insurmountable risks, without much cost." This allows for critical project decisions to be made before significant investment.

Hint

The Spiral model is intrinsically risk-driven, with risk analysis at its core.