COS 102 2 lecture week 3 Objective Question

Question

In Extreme Programming (XP), what activity is highlighted as the key activity throughout a software project?
Options
A Coding
Correct Answer
B Extensive upfront design
C Formal documentation
D Project planning and scheduling
Correct Answer

Option A is the correct answer.

Detailed Explanation

Page 67 explicitly states, "Coding is the key activity throughout a software project" in Extreme Programming (XP). This underscores XP's practical, code-centric approach.

Hint

XP is known for its iterative and hands-on approach, often emphasizing direct implementation.