Traditional method of evaluating project include all except
Options
A Internal Rate of Return
B Accounting Rate of Return
C Payback Period
D Gantt Chart
Correct Answer
Correct Answer

Option D is the correct answer.

Detailed Explanation

Gantt Chart is a visual tool used for project scheduling and planning, whereas IRR, ARR, and Payback Period are methods used for financial evaluation of projects.

Hint

Look for the option that is used for timeline scheduling rather than financial appraisal.