Question Detail

AMS 104 Past Questions AMS 104 1 Objective Question

Question

The method of analysing project is
Options
A Economic path method
B Financial path method
C Critical path method
Correct Answer
D Project path method
Correct Answer

Option C is the correct answer.

Detailed Explanation

Critical Path Method (CPM) is a step-by-step project management technique for process planning that identifies critical and non-critical tasks.

Hint

Think of the standard network analysis technique abbreviated as CPM.

Question Info