Meeting the need of customers and major stakeholders will require
Options
A Integrated project planning and control system
Correct Answer
B Knowing what their needs are
C Financial readiness
D Project acceptance
Correct Answer

Option A is the correct answer.

Detailed Explanation

An integrated project planning and control system ensures proper coordination, tracking, and delivery across all stakeholder requirements.

Hint

Think about a comprehensive planning and control system that connects all project elements.