Baseline data is used to:
Options
A Compare project performance against initial targets
Correct Answer
B Train employees
C Decorate offices
D Select equipment
Correct Answer

Option A is the correct answer.

Detailed Explanation

Baseline data serves as an initial reference point to measure subsequent performance[cite: 2].

Hint

What reference point is established at the start for comparison?