AMS 104 Past Questions AMS 104 2 Objective Question

Question

Cost-benefit analysis evaluates:
Options
A Financial viability of project outcomes
Correct Answer
B Employee lunch preferences
C Office furniture costs
D Equipment colors
Correct Answer

Option A is the correct answer.

Detailed Explanation

Cost-benefit analysis weighs financial costs against anticipated gains to check viability[cite: 2].

Hint

It compares financial expenditure to output value.