Question Detail

AMS 104 Past Questions AMS 104 2 Objective Question

Question

The triple constraint in project management includes:
Options
A Time, cost, scope
Correct Answer
B Employees, offices, equipment
C Quality, risk, stakeholders
D Budget, snacks, vacations
Correct Answer

Option A is the correct answer.

Detailed Explanation

The triple constraint balance consists of time, cost, and scope[cite: 2].

Hint

Which triad defines the classic project management triangle?