Change control processes ensure:
Options
A Structured handling of scope changes
Correct Answer
B Employee promotions
C Office relocations
D Equipment replacements
Correct Answer

Option A is the correct answer.

Detailed Explanation

Change control provides formal structure for assessing and approving changes to project baseline[cite: 2].

Hint

How are adjustments to requirements managed without chaos?