Question Detail

AMS 104 Past Questions AMS 104 2 Objective Question

Question

Agile project management emphasizes:
Options
A Iterative development and flexibility
Correct Answer
B Rigid plans
C No stakeholder input
D Fixed budgets only
Correct Answer

Option A is the correct answer.

Detailed Explanation

Agile methodologies promote iterative cycles, flexibility, and rapid feedback adaptation[cite: 2].

Hint

Look for flexibility and iterative cycles.