AMS 104 Past Questions AMS 104 2 Objective Question

Question

A milestone in project management marks:
Options
A A significant event or achievement
Correct Answer
B Employee vacations
C Office parties
D Equipment purchases
Correct Answer

Option A is the correct answer.

Detailed Explanation

Milestones mark key progress points or completed major phases[cite: 2].

Hint

What zero-duration marker signals major project progress?