Which document is created during the initiation phase to formally authorize a project?
Options
A Project plan
B Feasibility study
C Project charter
Correct Answer
D Risk register
Correct Answer

Option C is the correct answer.

Detailed Explanation

The project charter gives authority to proceed with the project[cite: 3].

Hint

Identify the official charter that gives formal permission to proceed.