Question Detail

AMS 104 Past Questions AMS 104 3 Objective Question

Question

What happens during the monitoring and controlling phase?
Options
A Deliverables are handed over
B Performance is tracked against the plan
Correct Answer
C The charter is created
D Risks are identified
Correct Answer

Option B is the correct answer.

Detailed Explanation

This phase ensures that the project stays aligned with the plan by tracking performance[cite: 3].

Hint

Look for tracking and measuring against the baseline plan.