Question Detail

AMS 104 Past Questions AMS 104 3 Objective Question

Question

Which of the following is a key activity in the initiation phase?
Options
A Developing a detailed project schedule
B Conducting a feasibility study
Correct Answer
C Executing project tasks
D Monitoring project quality
Correct Answer

Option B is the correct answer.

Detailed Explanation

Conducting a feasibility study during initiation helps determine if the project is viable and worth pursuing[cite: 3].

Hint

Assessing viability before committing major resources.