Question Detail

AMS 104 Past Questions AMS 104 3 Objective Question

Question

Which of these is NOT typically part of project initiation?
Options
A Defining high-level requirements
B Developing detailed work packages
Correct Answer
C Identifying key stakeholders
D Creating a business case
Correct Answer

Option B is the correct answer.

Detailed Explanation

Developing detailed work packages happens during planning, not initiation[cite: 3].

Hint

Granular task breakdown is reserved for planning.

Question Info