During which phase would you most likely create a Work Breakdown Structure (WBS)?
Options
A Initiation
B Planning
Correct Answer
C Execution
D Monitoring and Controlling
Correct Answer

Option B is the correct answer.

Detailed Explanation

The WBS is defined during planning to decompose project scope into smaller work items[cite: 3].

Hint

Which phase decomposes scope before work begins?