Which document would you update when encountering scope changes?
Options
A Project charter
B Scope baseline
Correct Answer
C Feasibility study
D Team roster
Correct Answer

Option B is the correct answer.

Detailed Explanation

When scope changes are formally approved, the scope baseline is updated[cite: 3].

Hint

The official scope reference point that gets updated.