Question Detail

AMS 104 Past Questions AMS 104 3 Objective Question

Question

What is the primary output of the initiation phase?
Options
A Completed deliverables
B Approved project charter
Correct Answer
C Detailed schedule
D Quality metrics
Correct Answer

Option B is the correct answer.

Detailed Explanation

An approved project charter is the definitive output authorizing project movement to planning[cite: 3].

Hint

The document that authorizes proceeding to planning.

Question Info