AMS 104 Past Questions AMS 104 3 Objective Question

Question

Which of these is a key monitoring and controlling activity?
Options
A Writing code for software
B Comparing actual vs. planned performance
Correct Answer
C Creating the business case
D Celebrating project completion
Correct Answer

Option B is the correct answer.

Detailed Explanation

Comparing actual performance metrics against baseline plans highlights variances for corrective action[cite: 3].

Hint

Evaluating actual metrics against planned baselines.