If a project's budget is reduced by 20%, which two constraints are most affected?
Correct Answer
Option C is the correct answer.
Detailed Explanation
Cutting budget generally forces cuts to deliverables (scope) or compromises standard quality[cite: 3].
Hint
Less money forces cuts to deliverable volume or output standard.