Question
Which constraint is primarily concerned with deadlines and schedules?
Correct Answer
Option B is the correct answer.
Detailed Explanation
The time constraint governs schedules, activity durations, and project deadlines[cite: 3].
Hint
Relates directly to timelines and target completion dates.