Question

What is the impact of unrealistic time estimates?
Options
A Projects finish early
B Team motivation improves
C Schedule delays become likely
Correct Answer
D Budgets decrease
Correct Answer

Option C is the correct answer.

Detailed Explanation

Setting overly optimistic or aggressive time targets results in schedule slippage[cite: 3].

Hint

Setting overly optimistic deadlines leads to missed targets.