Which phase involves creating a project charter?
Options
A Planning
B Initiation
Correct Answer
C Execution
D Closing
Correct Answer

Option B is the correct answer.

Detailed Explanation

Project charters are created during Initiation to authorize the project[cite: 3].

Hint

The phase that authorizes initial project setup.