What triggers the Initiation phase?
Options
A Completion of the previous project
B A business need or opportunity
Correct Answer
C Team vacations
D Random selection
Correct Answer

Option B is the correct answer.

Detailed Explanation

A business requirement, problem, or market opportunity initiates a project[cite: 3].

Hint

An organizational need or market opportunity.