AMS 104 Past Questions AMS 104 5 Objective Question

Question

One of these is the consideration for chosen appropriate project management structure:
Options
A Organizational consideration
Correct Answer
B Financial consideration
C Marketing consideration
D Cost consideration
Correct Answer

Option A is the correct answer.

Detailed Explanation

Organizational context (culture, authority lines, environment) dictates the selection of project structure (e.g., matrix, functional)[cite: 4].

Hint

Structure choices primarily stem from internal organizational design.