Question

The following are internal constraints for project delays EXCEPT:
Options
A Monopoly of technology
B Managerial incompetency
C Lack of skilled workers
D Law and order problem
Correct Answer
Correct Answer

Option D is the correct answer.

Detailed Explanation

Law and order problems are external political/environmental constraints, whereas incompetency, skill gaps, and technological bottlenecks are internal constraints[cite: 4].

Hint

Which option is an external societal issue rather than an internal organizational factor?