Question Detail

AMS 104 Past Questions AMS 104 2 Objective Question

Question

Project evaluation primarily aims to:
Options
A Assess project success against objectives
Correct Answer
B Hire new team members
C Decorate the office
D Purchase equipment
Correct Answer

Option A is the correct answer.

Detailed Explanation

The main goal of evaluation is to measure whether a project met its intended goals[cite: 2].

Hint

Focus on checking if project objectives were met.

Question Info