Question

Which is NOT a phase of project evaluation?
Options
A Planning
B Execution
C Post-implementation review
D Employee training
Correct Answer
Correct Answer

Option D is the correct answer.

Detailed Explanation

Employee training is an implementation or HR activity, not a phase in evaluation[cite: 2].

Hint

Which option is an operational activity rather than an evaluation stage?