A Work Breakdown Structure (WBS) breaks down:
Options
A Project deliverables into smaller tasks
Correct Answer
B Employee salaries
C Office budgets
D Equipment lists
Correct Answer

Option A is the correct answer.

Detailed Explanation

A WBS decomposes major deliverables into smaller, manageable work components[cite: 2].

Hint

Decomposing deliverables into sub-components.