Question Detail

AMS 104 Past Questions AMS 104 2 Objective Question

Question

PERT is used for projects with:
Options
A Uncertain task durations
Correct Answer
B Only fixed deadlines
C No stakeholders
D No budget
Correct Answer

Option A is the correct answer.

Detailed Explanation

PERT uses probabilistic estimates (optimistic, pessimistic, most likely) for uncertain durations[cite: 2].

Hint

Which technique handles time estimation under uncertainty?

Question Info