What is an example of a deliverable in the initiation phase?
Options
A Completed software
B Project charter
Correct Answer
C UI design
D Test results
Correct Answer

Option B is the correct answer.

Detailed Explanation

The charter is a key document generated during initiation[cite: 3].

Hint

Which document formally kickstarts a project?