Question Detail
Question
Which phase runs concurrently with execution?
Correct Answer
Option B is the correct answer.
Detailed Explanation
Monitoring and controlling happens alongside execution to ensure the project stays on track[cite: 3].
Hint
Which oversight phase takes place at the exact same time tasks are executed?