Question Detail

AMS 104 Past Questions AMS 104 3 Objective Question

Question

Which phase runs concurrently with execution?
Options
A Initiation
B Monitoring and controlling
Correct Answer
C Planning
D Closing
Correct Answer

Option B is the correct answer.

Detailed Explanation

Monitoring and controlling happens alongside execution to ensure the project stays on track[cite: 3].

Hint

Which oversight phase takes place at the exact same time tasks are executed?