AMS 104 Past Questions AMS 104 3 Objective Question

Question

What is the consequence of poor monitoring and controlling?
Options
A Projects always finish early
B Issues may go undetected
Correct Answer
C Stakeholders become unnecessary
D Planning becomes easier
Correct Answer

Option B is the correct answer.

Detailed Explanation

Inadequate control allows schedule slips, budget overruns, and technical issues to escalate undetected[cite: 3].

Hint

Problems escalate quietly without tracking.