Which three elements form the "Iron Triangle" of project management?
Options
A Scope, Quality, Risk
B Time, Cost, Quality
C Scope, Time, Cost
Correct Answer
D Resources, Risk, Quality
Correct Answer

Option C is the correct answer.

Detailed Explanation

The Iron Triangle (triple constraints) consists of Scope, Time, and Cost[cite: 3].

Hint

The core triad balancing project work, timeline, and budget.