Question Detail

AMS 104 Past Questions AMS 104 3 Objective Question

Question

Which constraint would be most affected by adding new features to a software project mid-way?
Options
A Time
B Cost
C Scope
Correct Answer
D All three equally
Correct Answer

Option C is the correct answer.

Detailed Explanation

Adding deliverables or features directly expands project scope[cite: 3].

Hint

Features directly define what is included in the project deliverables.