Question
If a project must be completed earlier than planned, what two constraints are most likely to be impacted?
Correct Answer
Option C is the correct answer.
Detailed Explanation
Shortening the timeline usually requires spending more money (crashing) or reducing deliverables (scope)[cite: 3].
Hint
To finish faster, you must spend more or do less.