What is the most likely consequence of inadequate project planning?
Correct Answer
Option C is the correct answer.
Detailed Explanation
Poor planning causes unexpected obstacles, bottlenecks, and timeline delays[cite: 3].
Hint
Poor groundwork leads to missed deadlines.