How can frequent change orders impact a project?
Options
A Improve team morale
B Reduce project costs
C Cause schedule delays
Correct Answer
D Eliminate all risks
Correct Answer

Option C is the correct answer.

Detailed Explanation

Frequent change orders disrupt ongoing work and push back delivery schedules[cite: 3].

Hint

Constant changes interrupt workflow and slip timelines.