Which phase of the project life cycle involves defining the project at a high level and securing approval?
Options
A Planning
B Execution
C Initiation
Correct Answer
D Closing
Correct Answer

Option C is the correct answer.

Detailed Explanation

The initiation phase focuses on defining the high-level business objective and obtaining approval to begin[cite: 3].

Hint

The phase that defines initial scope and obtains approval.