During which phase are detailed project plans developed?
Options
A Monitoring and Controlling
B Planning
Correct Answer
C Execution
D Closing
Correct Answer

Option B is the correct answer.

Detailed Explanation

Detailed sub-plans for schedule, cost, quality, and risk are built in the planning phase[cite: 3].

Hint

Phase dedicated to creating step-by-step management plans.