Question Detail
Question
If a project must be completed sooner, what is a likely trade-off?
Correct Answer
Option A is the correct answer.
Detailed Explanation
To compress time, you must either add resources (higher cost) or cut deliverable features (reduced scope)[cite: 3].
Hint
Spend more money or cut down deliverables.