Question Detail

AMS 104 Past Questions AMS 104 4 Objective Question

Question

Which is NOT a strategy to manage triple constraints?
Options
A Prioritizing one constraint over others
B Regularly reviewing project progress
C Ignoring stakeholder input
Correct Answer
D Using change control processes
Correct Answer

Option C is the correct answer.

Detailed Explanation

Ignoring stakeholder input damages project alignment and is not a valid management strategy[cite: 3].

Hint

Identify the non-viable management behavior.

Question Info