AMS 104 Past Questions AMS 104 5 Objective Question

Question

What is a key advantage of the project life cycle?
Options
A Guarantees zero risks
B Provides a structured framework for management
Correct Answer
C Eliminates the need for stakeholders
D Allows unlimited budget changes
Correct Answer

Option B is the correct answer.

Detailed Explanation

The life cycle offers a organized structure for project oversight[cite: 3].

Hint

Structured baseline framework.